National Grid Removes Two 180-Tonne Transformers at Pelham Substation

Pelham, United Kingdom – October 12, 2026 -- National Grid has removed two transformers, each weighing about 180 tonnes, from Pelham Substation, clearing the site for two new 300-tonne quad boosters due between February and April 2027 under its North London Reinforcement (NLR) project.

The units had been in service for around 35 years. Contractors Murphy and Equans worked with National Grid on the removal, with around 20 people involved in planning and execution.